At the mid-year point in its first year, SPO has moved ahead on several of its goals. Its successes seem especially marked considering that the staffing picture is still not complete. Our focus has been on the development of tools and methods, with development work going on using Quark and Quark Avenue, Logictran's rtf2xml converter and Cocoon.We have also worked on assembling a body of content and now have working agreements with several journals and are in discussions with several more. Work for the ACLS History eBook project has also begun, with some test files received and experimentation with delivery underway. The books for the History eBook backfile will be arriving shortly. Although some work has been done in promoting our services and capabilities on campus, we have fallen behind in this area; work on information materials and the web site is going on now. We have also fallen a bit behind in planning further development of our management systems -- partly because of not having a formal programmer in place and partly because there has not yet been a real demand for these services. This work will also take priority in the months ahead. Activities scheduled for the remainder of the year include beginning work on specifications for a peer review mechanism and development work on statistics and on charging mechanisms.
| Timeline: | October-March | |
| Responsibility: | Rosenblum with assistance of hourly worker, and input from Bonn | |
| Status: | Have compiled list of about 55 publishers. Survey has been sent out to Humanities journal editors. Now awaiting responses. |
| Timeline: | Ongoing | |
| Responsibility: | Bonn | |
| Status: | Although no specific activity has gone on in this area, there is a meeting scheduled with Earl Lewis, Dean of Rackham to discuss the publishing initiative. |
| Timeline: | To be determined. Possible first meeting at midwinter ALA. | |
| Responsibility: | Bonn | |
| Status: | DLF has agreed to sponsor meeting. We are currently deciding on the invitees and a date. |
| Timeline: | To be determined. Possibly in conjunction with All things Digital. Aim for a speaker by March. | |
| Responsibility: | Bonn | |
| Status: | No activity in this area, but staff did attend talk by Highwire representative at Rackham event on digital publishing. |
| Timeline: | Ongoing with milestones as noted | |
| Responsibility: | All staff, coordinated by Bonn | |
| Status: | Web site and brochure are currently in development, slated to conclude in mid-March. Bonn has met with Wanda Monroe to discuss PR possibilities. Bonn has also met with Senior Managers and with Special Collections to discuss the publishing initiative. |
| Timeline: | Ongoing | |
| Responsibility: | All staff, coordinated by Bonn | |
| Status: | Staff members have attended sessions in the Elcectonic Humanist series sponsered by the Institute for the Humanities, the SI Copyright symposium and talks sponsered by Rackham on publishing. |
| Timeline: | Ongoing | |
| Responsibility: | Rosenblum, Bonn | |
| Status: | Bonn talked to about 20 Humanities journal editors at a session sponsored by the Institute for the Humanities. Much work remains to be done in getting the word out on campus about SPO's mission and services. |
| Timeline: | by end of November | |
| Responsibility: | Rosenblum, Programmer | |
| Status: | This is essentially done, although some changes have been made in the process -- i.e. using a stand-alone script rather than textclass and no longer using Quark. |
| Timeline: | Ongoing | |
| Responsibility: | Rosenblum, Interface Specialist, Programmer as needed | |
| Status: | Routines are now in place and will be tested when the second PI article arrives in March. |
| Timeline: | by end of November | |
| Responsibility: | Rosenblum | |
| Status: | Most of this has been done. A few final adjustments need to be made -- awaiting programming time from DLPS. |
| Timeline: | September-February, first issue online June | |
| Responsibility: | Rosenblum, Interface Specialist | |
| Status: | All in process |
| Timeline: | Milestones as noted. Backfile conversion complete by end of year. | |
| Responsibility: | Conversion of existing electronic files coordinated by Rosenblum, other conversion activities coordinated by Bonn. | |
| Status: | Backfiles have been scanned and are now in QC. Existing electronic files are nearly completely encoded in XML and will go online in March. |
| Timeline: | October-May with milestones as noted | |
| Responsibility: | Rosenblum coordinates, Interface Specialist | |
| Status: | Permission to digitize has been obtained and digitization is scheduled with Preservation pending hiring of a scanning operator. |
| Timeline: | Dependent on Media Union staff and CoE | |
| Responsibility: | Bonn for proposal, others to be determined as project takes shape. | |
| Status: | Proposal went forward and was greeted with interest by CoE administration. Currently awaiting funding to move forward. |
| Timeline: | Ongoing, depending on directions determined by Rackham and the Library. | |
| Responsibility: | Dependent on types of tasks to be determined | |
| Status: | No activity in this area. |
| Timeline: | Ongoing | |
| Responsibility: | Bonn | |
| Status: | There have been several conversations about publishing Special Collections resources. Work is also underway to create an electronic version of the BHL volume on Women in the Early Years at UM. |
| Timeline: | Ongoing with initial analysis and specification in December | |
| Responsibility: | Interface Specialist, Programmer | |
| Status: | Staff conducted inititial assessment and discussed with DLPS-IR group. |
| Timeline: | Dependent on ACLS timelines | |
| Responsibility: | All staff as appropriate, working with DLPS | |
| Status: | No monographs have been received. |
| Timeline: | Education and training September-December, implementation dependent on arrival of content, availability of browsers with xml support | |
| Responsibility: | Rosenblum, Interface Specialist | |
| Status: | Experimentation has been underway with Cocoon and associated style sheets applied to demo files from ACLS. |
| Timeline: | July for specification, August for implementation | |
| Responsibility: | DLPD staff with CS | |
| Status: | Done |
| Timeline: | Specifications in February, implementation dependent on programmer hire | |
| Responsibility: | Interface specialist, Programmer | |
| Status: | Staff fell behind on this activity. Completion of Programmer hire (now underway) should stimulate activity in this area. |
| Timeline: | Internal assessment, November. Work with editors, February and on. | |
| Responsibility: | Rosenblum, Bonn | |
| Status: | Existing system seem sufficient.Awaiting demand for service to test. |
| Timeline: | Initial assessment January then ongoing depending on ACLS timelines | |
| Responsibility: | Programmer with CS, Interface Specialist, Bonn with contributions from ACLS project staff | |
| Status: | Bonn is currently writing document on charging possibilities. ACLS does not yet require this service, so there has been little pressure to work in this area. Bonn will share document with ACLS participants at meeting in May. |
| Timeline: | by end of December | |
| Responsibility: | Bonn assisting Preservation staff as needed. | |
| Status: | Discussions have been held with ACME Bookbinding. Library has decided to develop RFP to solicit vendor responses. |
| Timeline: | January, dependent on Preservation staff | |
| Responsibility: | Bonn assisting Preservation staff as needed. | |
| Status: | This issue has been discussed in CMDC. There is now a small working group resolving seveal of the issues around Print on Demand. |
| Timeline: | February-March, dependent on Preservation staff | |
| Responsibility: | Bonn assisting Preservation staff as needed. | |
| Status: | See 6.2 |
| Timeline: | February-March, dependent on Preservation staff | |
| Responsibility: | Bonn assisting Preservation staff as needed. | |
| Status: | See 6.2 |
| Timeline: | by end of year | |
| Responsibility: | Bonn assisting Preservation staff as needed. | |
| Status: | See 6.2 |
| Timeline: | Initial assessment March then ongoing depending on ACLS timelines | |
| Responsibility: | Rosenblum, Bonn, with contributions from ACLS project staff | |
| Status: |
| Timeline: | Initial April-May then ongoing depending on ACLS timelines | |
| Responsibility: | Programmer with CS/HZ, Interface Specialist, Bonn with contributions from ACLS project staff | |
| Status: | To be done |
| Timeline: | Dependent on ACLS timelines | |
| Responsibility: | Interface Specialist, Bonn with contributions from ACLS project staff | |
| Status: | To be done |
| Timeline: | ASAP depending on approval from O. Feinstein | |
| Responsibility: | Bonn, Sheppard | |
| Status: | First release is done. Currently collecting infomration for updating directory (updates are coordinated by Chuck Ransom). |
| Timeline: | Dependent on approval from Skib/Amman | |
| Responsibility: | Sheppard | |
| Status: | This project is moving very slowly. SPO has completed the first online version but Amman wants to udertake considerable revision and additions before releasing. |
| Timeline: | by January | |
| Responsibility: | Rosenblum | |
| Status: | Data is prepared and is waiting for Wilkin to put online, pending completion of the bibclass revision.Becky Dunkle is looking into resources for supplementing the records with reel numbers. |
| Timeline: | ASAP depending on approval from Herrada | |
| Responsibility: | Sheppard | |
| Status: | Done |
| Timeline: | by January 31 | |
| Responsibility: | Bonn | |
| Status: | All but a handful of texts are now online. Handbook and final report preparation are underway. |
| Timeline: | ongoing | |
| Responsibility: | Bonn, Sheppard | |
| Status: | AOC process is smoothly in place and low demand. MoAA is in planning for phase 2 and Bonn is actively part of that process. Saline Historical Photos are digitized and online. |